Optimized Feasibility Study

On January 22, 2007 Yukon Zinc announced the results of the Optimized Feasibility Study (OFS) on the Wolverine Project completed by prime consultant Wardrop Engineering Inc. and the sub-consultants. Wardrop was engaged to prepare the study in accordance with the Standards of Disclosure for Mineral Projects as defined in National Instrument 43-101. Wardrop concluded that “technically and economically, the Wolverine Project is a viable project”.

Average Annual Production

Average Annual Production
Metal in Concentrates
Contained Metal -- 1400 tpd Undiluted Ore
Zinc 53,450 t          (117.8 M pounds)
Copper 4,680 t            (10.3 M pounds)
Lead 5,860 t            (12.9 M pounds)
Silver 4,933,000 oz
Gold 20,200 oz

*Estimates based on average annual production (for first three years) in concentrates

Wolverine Project Economics

The economics of the project have been estimated using a large range of metal price scenarios to reflect historic and current prices. The Wardrop financial analysis is on a pre-tax basis that does not include corporate income tax or Yukon mining royalties. Using these price scenarios, the project economics indicate a large range of potential outcomes.

 Metal Price Scenarios
Based on assumptions in Wardrop Jan 2007 Optimized Feasibility Study
2-yr backward Avg.
3 yr backward Avg.
Price at
(Nov, 2006)
NPV 8% pre-tax                  
$184.2 MM
$104.8 MM
$571.7 MM
Internal Rate of Return  (pre-tax)       
26.3%
18.9%
56.8%
3 yr Cumulative Cash flow ('09-2011)
$217.7 MM
$172.5 MM
$439.3 MM
Payback Period            yrs            
3.0
3.9
1.5

Wardrop Metal Price Scenarios (US dollars)
 
2-Yr Backward Avg.
3 yr backward Avg.
Price at
(Nov, 2006)
Zinc - US$/lb
$1.07
$0.87
$1.84
Silver - US$/oz
$9.48
$8.54
$12.69
Copper - US$/lb
$1.85
$1.85
$1.85
Gold - US$/oz
$526
$487
$626
Lead - US$/lb
$0.52
$0.48
$0.76
Exchange Rate
0.855
0.82
0.847

Capital Costs

Estimated capital costs as at January 2007 (excluding working capital requirements) include direct and indirect costs, and aggregate $175.6M before contingency of $24.3M and $7.6M in owner’s costs. The estimated capital costs are based on all new equipment and are as follows:

Estimated Capital Costs
Wardrop Direct Costs (CAD$M) Wardrop Indirect Costs (CAD$M)
Site preparation and roads $23.1 Engineering and procurement $8.5
Mill and process $49.6 Construction management $8.6
Power generation $0.9 Construction indirects $11.1
Tailings & water supply and reclaim $9.0 Materials and inventory $3.2
Service facilities and mobile $15.5 Duties and freight $4.5
Permanent camp $5.7 Commissioning $0.8
Mining $35.1    
Subtotal $139.9   $36.7
Sub Total $175.6
Contingency $24.3
Owner’s Costs $7.6
Total $207.5

Operating Costs

Estimated life-of-mine unit operating costs are determined on a cost per tonne mined basis and aggregate $95.58 per tonne as follows:

Operating Costs
Cost Centre
CAD $/tonne mined
Mining
$42.18
Milling
$14.49
Maintenance
$8.45
General and Administration
$15.25
Power
$15.21
Total
$95.58

Metallurgy

Metallurgy
 
Assays
Recoveries
Product
Tonnes
Zn %
Cu %
Pb %
Ag  g/t
Au g/t
Zn %
Cu %
Pb %
Ag %
Au %
ROM
5,151,459
9.66
0.91
1.26
281.8
1.36

 

 

 

 

 

Post DMS
4,238,149
11.70
1.10
1.52
340.86
1.64

 

 

 

 

 

Cu conc
174,397
3.74
21.30
2.25
4409
11.3
1.2
79.9
8.0
60.0
33.4
Pb conc
132,958
12.4
1.97
22.30
1625
13.5
2.4
4.3
46.0
12.9
23.2
Zn conc
818,274
54.2
0.36
0.98
151
0.74
89.4
6.7
17.2
10.2
10.9

Infrastructure and Transportation

The project area is currently accessed by a 24km mine access road that connects Wolverine to the Robert Campbell Highway and an 800 metre long gravel airstrip. Yukon Zinc plans to extend the airstrip to 1200 metres and upgrade the surface for larger aircraft required for transport of construction and mine personnel. The development plan provides for the construction of a 150 person camp at the mine site to house workers at the mine during both construction and operations. Initial construction work will be supported from the 50-man exploration camp.

Zinc, copper and lead concentrates are to be trucked approximately 860 kilometres to concentrate loading facilities in the port of Stewart, British Columbia for trans-shipment to smelters in Asia. The high content of silver and gold in the copper and lead concentrates increases their unit value and reduces the impact of high transportation costs.

> See full Optimized Feasibility Study News Release
> See pictures from Wolverine


   
Home | Company | News | Investors | Development | Exploration | Social Responsibility | Contact Us | Site Search | Site Map
Copyright 2006. All Rights Reserved. Disclaimer