Milestones

2010
June 2010
Installed rod/ball mills, flotation circuits and conveyors
2009
Sept 2009 Enclosed Mill Complex Buildings
May 2009
New 205 person camp is installed
Feb 2009
Prepared for construction season
2008
Fall 2008
Earthworks continued at Wolverine Project
July 2008
JDC and NWII acquired all shares of Yukon Zinc
2007
Oct 2007 Secured Type A Water License
Sep 2007 Yukon Zinc Announced Completion of Wolverine Access Road
Jan 2007 Completed Optimized Feasibility Study by Wardrop Engineering indicated strong project economics
2006
Dec 2006

Quartz Mining License received for mine construction

June 2006
Added Raymond Mah as Chief Operating Officer and other development team members secured
May 2006
Completed Hatch Feasibility Study


 